Fragrance Development Process

A detailed 10-stage guide to developing your fragrance product — from initial brief through to post-launch support. Each stage includes timelines, deliverables, and key decision points.

10

Key Stages

12-16

Weeks (typical)

500+

Unit MOQ

1

Project Brief

1-2 days

Define your fragrance vision, target market, quantities, timeline, and budget. This is the foundation for everything that follows.

Client Brief

  • Fragrance type and market positioning (luxury, masstige, mass)
  • Target audience demographics and psychographics
  • Volume and production quantities
  • Launch date and project timeline
  • Budget parameters and constraints

Component Design Requirements

  • Bottle and vessel specifications
  • Pump mechanism selection
  • Collar design preferences
  • Cap and closure functionality
  • Preferred decoration techniques
2

Concept & Feasibility

3-5 days

Develop initial design direction, assess technical feasibility, and evaluate stock versus custom component options.

Design Inspiration & Moodboard

  • Initial aesthetic direction development
  • Trend analysis and market research
  • Competitor benchmarking
  • Material exploration and options

Technical Feasibility Assessment

  • Stock vs custom mould evaluation
  • MOQ and timeline compatibility
  • Component compatibility analysis
  • Manufacturing capability assessment
  • Budget impact analysis
3

Component Selection & Mould Decision

1-2 weeks

Choose between stock moulds from our library of 100+ designs or commission bespoke components through our global supply network.

Stock Mould Route

  • Browse existing mould library
  • Review 3D visuals and specifications
  • Assess material and finish options
  • Evaluate customisation possibilities
  • Fast-track to prototyping

Custom Mould Route

  • Create bespoke CAD designs
  • Generate 3D renderings for review
  • Engineering design finalisation
  • Tooling cost estimation
  • Timeline projection and planning
4

Sampling

2-3 weeks

Produce physical samples for evaluation — clear glass, decorated finishes, and component fit testing.

Stock Mould Sampling

  • Clear stock sample production
  • Material and finish samples
  • Decoration application tests
  • Colour matching trials

Custom Mould Sampling

  • Technical drawing creation and approval
  • CNC sample production (3D print or resin)
  • Pre-tooling review and modifications
  • Final approval before mould creation

Sample Review Criteria

  • Aesthetic evaluation
  • Functionality testing (pump, spray, seal)
  • Ergonomic fit and feel assessment
  • Brand alignment verification
5

Tooling (If Custom Mould)

4-6 weeks

For bespoke components, precision moulds are fabricated and tested. This stage is skipped entirely with stock moulds.

Tool Manufacturing Process

  • Precision mould fabrication
  • Quality control checkpoints
  • First article inspection
  • Sample production for review
  • Revision iterations if needed
  • Final production approval
6

Decoration & Branding

1-2 weeks

Apply branding and decoration to your components — from screen printing and hot stamping to spray coating and electroplating.

Decoration Techniques

  • Screen printing setup
  • Hot stamping die creation
  • Custom Pantone colour matching
  • Metallic foiling application
  • Etching and engraving patterns
  • Debossing and embossing details
  • Electroplating finish options

Brand Application

  • Logo placement optimisation
  • Typography selection and sizing
  • Regulatory text integration
  • Quality mark positioning
7

Testing & Compliance

1-2 weeks

Rigorous testing ensures your product meets all performance, safety, and regulatory standards before production.

Component Testing Protocols

  • Fragrance compatibility verification
  • Leak and pressure testing
  • Drop test certification
  • Temperature stability assessment
  • UV resistance evaluation

Regulatory Compliance

  • REACH compliance verification
  • IFRA standards conformity
  • Market-specific regulations
  • Safety assessment documentation
  • Certificate of conformity
8

Final Approval & Production

4-8 weeks

With all approvals in place, full-scale production begins — mixing, filling, assembly, and batch documentation.

Pre-Production Setup

  • Final client sign-off
  • Production schedule planning
  • Raw material procurement
  • Quality control protocol setup

Mass Production Execution

  • Component manufacturing
  • Decoration application
  • Assembly line setup
  • Fragrance filling (if applicable)
  • Batch coding and serialisation
9

Quality Control & Delivery

1 week

Every batch is inspected, tested, and documented before being palletised and dispatched to your specified location.

Quality Assurance

  • Visual inspection protocols
  • Functional testing procedures
  • Random sampling checks
  • Batch documentation review
  • Certificate of analysis

Logistics & Delivery

  • Packaging and palletisation
  • Shipping documentation
  • Customs clearance support
  • Track and trace setup
  • Delivery confirmation
10

Post-Launch Support

Ongoing

Our partnership continues after delivery — reorder management, stock monitoring, and planning for future product lines.

Continuous Partnership

  • Reorder management system
  • Stock level monitoring
  • Forecast-based planning
  • Product line extensions
  • Market feedback integration
  • Future innovation planning

Typical Timelines

How long your project takes depends on complexity and whether you use stock or bespoke components.

Fast-Track

Approximately 12 weeks

Stock fragrances, stock components, and standard decoration. Ideal for speed-to-market launches.

Skips Stage 5 (Tooling) entirely.

Standard

6 to 9 months

Bespoke fragrance development with some custom elements in componentry or packaging design.

Most common timeline for new brands.

Complex Bespoke

12+ months

Custom glass moulds, master perfumer collaboration, and luxury finishing from scratch.

For prestige and luxury brands requiring maximum exclusivity.

Development Process FAQs

How long does the entire development process take?

The total timeline depends on your project complexity. Fast-track projects using stock components and fragrances can be completed in approximately 12 weeks. Standard projects with some bespoke elements typically take 6 to 9 months. Complex bespoke projects involving custom glass moulds and luxury finishing may take 12 months or longer.

Can steps be done in parallel to speed things up?

Yes. Several stages can overlap. For example, fragrance development can run alongside componentry selection, and decoration development can begin while tooling is in progress. Your account manager will map out the most efficient critical path for your specific project.

What if I want to use stock moulds instead of custom?

Using stock moulds from our library of over 100 designs significantly reduces your timeline by eliminating the tooling stage entirely. You can move directly from sampling to decoration and production, saving 4 to 6 weeks.

How involved do I need to be at each stage?

Key approval points require your input — typically at brief sign-off, fragrance approval, sample approval, and final production sign-off. Between these milestones, your account manager handles the day-to-day coordination. We keep you updated throughout with regular progress reports.

What are the minimum order quantities?

Our minimum order quantities start from 500 units, which is significantly lower than most manufacturers who require 3,000 to 5,000 units minimum. This makes our process accessible for startups, limited editions, and test launches.

Do you handle regulatory compliance?

Yes. Regulatory compliance is integrated into the process at Stage 7 (Testing & Compliance). We manage REACH compliance, IFRA standards, CLP labelling, EU Cosmetics Regulation documentation, and safety assessments. Every product we manufacture leaves our facility fully compliant and market-ready.